Infographic showing 5-step DISCOM approval process for rooftop solar in India 2026: application, inspection, installation, net metering, commissioning with subsidy.
5-step DISCOM approval for rooftop solar India: Get approved in 30-60 days + claim ₹78K subsidy!

Navigating the DISCOM approval process is essential for legally installing rooftop solar in India and unlocking subsidies. This 4th blog post breaks it down step-by-step for hassle-free grid connection under PM Surya Ghar Muft Bijli Yojana.

Why DISCOM Approval Matters

DISCOMs (Distribution Companies) regulate grid-connected rooftop solar to ensure system safety, grid stability, and net metering eligibility. Skipping approvals risks fines, disconnection, or subsidy denial, as they verify feeder capacity and compliance with state regulations. In 2026, streamlined MNRE guidelines mandate approvals within 15-30 days to boost India’s 500 GW renewable target. Learn more on the MNRE website.

Step-by-Step DISCOM Approval Process

Follow these stages for rooftop solar DISCOM approval in India:

  1. Online Application Submission: Register on the National Portal or your state DISCOM portal (e.g., PSPCL for Punjab). Upload electricity bill (last 6 months), ID proof, site photos, and proposed system specs (1-10 kW capacity). Pay nominal fee (₹200-₹1000).
  2. Feasibility Check and Site Inspection: DISCOM schedules an engineer visit within 3-7 days to assess roof space, shading, transformer load, and wiring. They issue Technical Feasibility Approval if viable, specifying sanctioned solar capacity.
  3. Vendor Selection and Installation: Choose a DISCOM-registered vendor using ALMM-listed panels and BIS-certified inverters. Sign consumer-vendor agreement; install only after feasibility nod to avoid rejection. Check approved vendors on your DISCOM site.
  4. Net Metering Application: Submit single-line diagram, bill of quantities, completion report, system photos, and invoices via portal. DISCOM approves, installs bi-directional smart meter (often within 15 days), and verifies AC/DC wiring.
  5. Final Inspection and Commissioning: Post-installation inspection confirms compliance. DISCOM issues Synchronization Certificate and Commissioning Certificate, enabling grid export and subsidy release (within 30 days via DBT). Track subsidies on the national portal.

Documents Required for DISCOM Approval

Gather these essentials for quick processing—download checklists from your DISCOM portal:

DocumentPurposeKey Tips
Electricity Bill (last 6 months)Verify consumer & load detailsScan recent bills clearly
Aadhaar/PAN CardKYC & subsidy linkingLink to bank account early
Site/Layout Plan & PhotosAssess roof space & shadingInclude north-facing orientation
System Specs (Quotes/Agreement)Confirm ALMM panels & BIS invertersGet from registered vendor
Single-Line Diagram (SLD)Validate wiring & safetySubmit post-installation
Bank Passbook/Cancelled ChequeDirect subsidy transfer (DBT)Mandatory for ₹78,000 CapEx grant

Timelines and Common Delays

Expect 30-60 days total: 15 days for feasibility, 15 for net metering, 30 for subsidy. Delays arise from incomplete docs, meter shortages, or high demand—MNRE mandates DISCOMs stock smart meters. Pro tip: Track via portal and follow up weekly. Download full guidelines PDF.

Also Read: Complete Guide to Rooftop Solar Subsidies India

State-Wise Variations

While national MNRE standards apply, check your state’s DISCOM for tweaks:​

  • Punjab (PSPCL): Fast online portal; verify feeder capacity at PSPCL.​
  • Gujarat (UGVCL/PGVCL): Quickest approvals (~20 days) with high solar adoption.
  • Karnataka (BESCOM): Efficient net metering; vendor lists online.
  • Delhi (TPDDL/BRPL): Extra SDO clearance needed; track via DISCOM app.
  • Others: Maharashtra/Tamil Nadu follow suit—always use state portals for latest 2026 rules.

Tips to Speed Up Approval

  • Use registered vendors—they handle paperwork.​
  • Ensure 20% shadow-free roof space per kW.​
  • Avoid peak monsoon for inspections.
  • Track via National Portal for real-time status.​

Follow this DISCOM approval roadmap for rooftop solar in India to slash your bills by 100% and claim up to ₹78,000 in subsidies—achieving payback in just 4-6 years. Start your solar journey today: share your DISCOM or questions in the comments!

FAQs

What is the DISCOM approval process for rooftop solar in India?

It involves online application, feasibility check, installation by registered vendors, net metering, and final commissioning—typically 30-60 days under PM Surya Ghar.

How long does DISCOM approval take for rooftop solar in 2026?

MNRE mandates 15-30 days for feasibility and net metering; total process spans 30-60 days including subsidy release.

What documents are needed for rooftop solar DISCOM approval?

Electricity bills (6 months), Aadhaar/PAN, site photos, system specs, SLD, and bank details—submit via National Portal.

Is DISCOM approval mandatory for rooftop solar subsidies?

Yes, feasibility and commissioning certificates from DISCOM are required for ₹78,000 subsidy under PM Surya Ghar Muft Bijli Yojana.

Can I install rooftop solar without DISCOM net metering?

No, grid-connected systems need net metering approval for legal export and subsidies; off-grid skips it but loses benefits.